Evaluating The Scheduling of The Development Projects of Rural Electricity Network Distribution Using Critical Path Method
Author(s) -
Diqbal Satyanegara,
Widya Nur Bhakti Pertiwi
Publication year - 2022
Publication title -
jurnal riset ekonomi manajemen (rekomen)
Language(s) - English
Resource type - Journals
eISSN - 2614-2953
pISSN - 2580-8893
DOI - 10.31002/rn.v5i2.4174
Subject(s) - timeline , critical path method , schedule , project planning , project management , scheduling (production processes) , work breakdown structure , operations management , electricity , operations research , computer science , work (physics) , project management triangle , process management , engineering management , business , systems engineering , engineering , project charter , geography , electrical engineering , operating system , mechanical engineering , archaeology
Delay in the completion of a project is a problem that is often faced, it certainly has an impact on the entire project. CPM is one of the control tools to get a working picture of the project. In 2015, PT PLN South Banten Area made a Development Project of Rural Electricity Network Distribution in Banten. This project is held by an electrical installation services company, PT. Z, in June 2015.This project is due 150 days, PT. Z had defined time completion on 143 days, but the completion took 154 days. The type of research used in this research is quantitative research with analytical technique CPM approach. This research identified the least project schedule planning. There are three activities in this project schedule which are unlisted yet, therefore it affected the timeline of the project. Based on the CPM calculation, PT. Z could have shorten the work time down to 3 days with the cost of Rp 1.802.386.000
Accelerating Research
Robert Robinson Avenue,
Oxford Science Park, Oxford
OX4 4GP, United Kingdom
Address
John Eccles HouseRobert Robinson Avenue,
Oxford Science Park, Oxford
OX4 4GP, United Kingdom