The possibility of applying the program evaluation and review technique for construction project schedule management
Author(s) -
Сергей Владимирович Бовтеев,
Anastasiia Mishakova
Publication year - 2020
Publication title -
vestnik graždanskih inženerov
Language(s) - English
Resource type - Journals
ISSN - 1999-5571
DOI - 10.23968/1999-5571-2020-17-4-115-121
Subject(s) - duration (music) , schedule , computer science , project management , probabilistic logic , earned value management , project planning , scheduling (production processes) , operations research , key (lock) , reliability engineering , systems engineering , risk analysis (engineering) , industrial engineering , operations management , engineering , project charter , artificial intelligence , medicine , art , literature , computer security , operating system
The program evaluation and review technique (PERT) was developed and first used more than sixty years ago and is now well known. This technique allows taking into account the probabilistic nature of the work duration, so it is used for scheduling projects, where the duration of all or some of the works can not be clearly determined due to the high degree of uncertainty of the external environment in which such projects are carried out. However, the problem of controlling the terms of project activities and key events of the project based on the program evaluation and review technique has not been studied well enough. This article investigates the possibilities of applying the program evaluation and review technique to track and control the construction project schedule. An algorithm for using this method to predict the probability of timely occurrence of control points and completion of the entire project is presented.