Scale-Up and Demonstration of Fly Ash Ozonation Tech
Author(s) -
Larry La Buz,
Rui Afonso
Publication year - 2004
Language(s) - English
Resource type - Reports
DOI - 10.2172/895905
Subject(s) - software deployment , schedule , scale (ratio) , project manager , operations research , period (music) , operations management , engineering management , project management , engineering , computer science , systems engineering , software engineering , geography , operating system , physics , cartography , acoustics
This is the third quarterly report under DOE Cooperative Agreement No.: DE-FC26-03NT41730. Due a number of circumstances, mostly associated with subcontractor agreements, the actual beginning of the project was delayed from its original award date of March 5, 2003. DOE's Project Manager was kept informed (verbally) by PPL's Project Manager throughout this period. Because of this delay, this is the third quarterly report and it refers to the time period from October to December 2004. As the project is in its ''pre-deployment'' stage, no results are available. This report summarizes the ongoing activities and provides an updated schedule. No significant issues or concerns are identified