Optimization of Digging and Loading Equipment and Hauling for Overburden Production with Quality Capacity Methods and Queing Methods in East Pit, August 2017 Period Pt. Artamulia Tata Pratama, Site Tanjung Belit, Bungo, Jambi
Author(s) -
Mulya Gusman,
Y.M. Asri,
I. Prengki
Publication year - 2019
Publication title -
journal of physics. conference series
Language(s) - English
Resource type - Journals
SCImago Journal Rank - 0.21
H-Index - 85
eISSN - 1742-6596
pISSN - 1742-6588
DOI - 10.1088/1742-6596/1387/1/012106
Subject(s) - truck , overburden , excavator , digging , engineering , production (economics) , footprint , productivity , quality (philosophy) , environmental science , automotive engineering , mining engineering , civil engineering , geology , paleontology , macroeconomics , archaeology , economics , history , philosophy , epistemology
In the mining process, the availability of dump truck equipment and loading equipment will determine the sustainability of production which has an impact on productivity and efficiency. The purpose of this study is to optimize production on stripping the overburden using the queuing method, match factor. The location of the study was conducted at PT. Artamulia Tata Pratama, Tanjung Belit, site Bungo, Jambi in August 2017 – September 2017. The loading equipment used is the PC 1250 Komatsu Excavator and the Komatsu HD 465-7 dump truck. The simulation results of the number of dump trucks needed based on production capacity is 17 units while based on queuing theory there are 17 units. Where the actual dump trucks used were 19 units.