Publication year - 1981
Publication title -
journal ‐ american water works association
Language(s) - English
Resource type - Journals
SCImago Journal Rank - 0.466
H-Index - 74
eISSN - 1551-8833
pISSN - 0003-150X
DOI - 10.1002/j.1551-8833.1981.tb04672.x
Subject(s) - damages , supreme court , law , shut down , order (exchange) , good faith , faith , business , political science , engineering , finance , philosophy , theology , nuclear engineering
A conflict in construction caused a contractor to cease operations when no change order was issued by a sewer and water district whose sewer line was being relocated, and the district won its suit for damages. The Supreme Court of Utah overturned this decision, ruling that the absence of a change order allowed the contractor to proceed outside the terms or to shut down and declare the contract breached.