NORTH PORTAL - HOT WATER CALCULATION - CHANGE HOUSE FACILITY #5008
Author(s) -
R. Blackstone
Publication year - 1996
Language(s) - English
Resource type - Reports
DOI - 10.2172/862349
Subject(s) - piping , fixture , pressure drop , environmental science , water supply , engineering , marine engineering , mechanical engineering , mechanics , environmental engineering , physics
The purpose of this design analysis and calculation is to determine the demand for hot water and to size the supply main piping for the Change House Facility No.5008 in accordance with the Uniform Plumbing Code (UPC) (Section 4.4.1) and U.S. Department of Energy Order 6430.1A-1540. The method used for the calculations is based on Section 4.4.1. The first step is to determine the maximum pressure drop between the most remote plumbing fixture and the main supply. The pressure drop for the hot water system is based on the total length of the supply piping from the cold water supply source through the water heater to the most remote hot water outlet. Equivalent fixture units are then assigned using Section 4.4.1. For hot water, the values are reduced by 25 percent in accordance with the UPC. The demand load in gpm is then determined based on the number of fixture units. The demand load and the pressure drop between the source and the most remote fixture is used to determine the pipe size and the corresponding friction losses for a given flow velocity not to exceed 10 feet/second