Engineering task plan for BX/BY compressor upgrade
Author(s) -
R.G. Strand
Publication year - 1995
Publication title -
osti oai (u.s. department of energy office of scientific and technical information)
Language(s) - English
Resource type - Reports
DOI - 10.2172/41291
Subject(s) - upgrade , horsepower , task (project management) , work (physics) , piping , plan (archaeology) , engineering , air compressor , gas compressor , compressor station , civil engineering , computer science , systems engineering , mechanical engineering , automotive engineering , geology , operating system , paleontology
This Engineering Task Plan outlines the remaining work to be completed for the BX/BY Instrument Air upgrade. Initial work efforts were guided by Engineering Work Plan, ``BX-BY Compressor Upgrade`` dated 1-25-93 (see Attachment A) which is provided for information. The overall engineering task is to provide a permanent replacement for the instrument air supply system for the 241-BX/BY Tank Farms. The existing system consists of a 25 horsepower Worthington non-lube compressor and an Oriad air dryer. The existing equipment is dated, requires high maintenance and is located in a contaminated zone making it unusable. The BX/BY instrument air replacement unit will be one of the 100 SCFM generic air stations. This station will be permanently sited with the addition of drawing changes to provide a concrete foundation, air piping to existing lines and electrical power supply tie-ins

The content you want is available to Zendy users.

Already have an account? Click here to sign in.
Having issues? You can contact us here
Accelerating Research

Address

John Eccles House
Robert Robinson Avenue,
Oxford Science Park, Oxford
OX4 4GP, United Kingdom