Commercial-scale demonstration of the liquid phase methanol (LPMEOH{trademark}) process. Technical progress report No. 4, 1 April--30 June 1995
Publication year - 1995
Publication title -
osti oai (u.s. department of energy office of scientific and technical information)
Language(s) - English
Resource type - Reports
DOI - 10.2172/219154
Subject(s) - trademark , quarter (canadian coin) , engineering , scale (ratio) , environmental science , operations management , waste management , computer science , geography , archaeology , cartography , operating system
The Liquid Phase Methanol (LPMEOH{trademark}) demonstration project at Kingsport, Tennessee is a $213.7 million cooperative agreement between the US Department of Energy (DOE) and Air Products Liquid Phase Conversion Company, L. P.(the Partnership). A facility producing 260 TPD of methanol will be designed and constructed at a site located at the Eastman Chemical complex in Kingsport, Tennessee. The Partnership will own and operate the facility for the four-year demonstration facility operational period. This project is sponsored under the DOE`s Clean Coal Technology Program, and its primary objective is to ``demonstrate the production of methanol using the LPMEOH{trademark} process in conjunction with an integrated coal gasification facility.`` The project will also demonstrate the suitability of the methanol produced for use as a chemical feedstock or as a low sulfur dioxide, low nitrogen oxides alternative fuel in stationary and transportation applications. The project may also demonstrate the production of dimethyl ether (DME) as a mixed coproduct with methanol, if laboratory- and pilot-scale research shows promising results. If implemented, the DME would be produced during the last six months of the operations phase. During this last quarter the project transitioned to the design phase. the project requires review under the National environmental Policy Act to move to the construction phase, which is scheduled to begin in August of 1995. DOE has prepared an Environmental Assessment, and a Finding of No Significant Impact was issued during this quarter. The facility is scheduled to be mechanically complete in November of 1996
Accelerating Research
Robert Robinson Avenue,
Oxford Science Park, Oxford
OX4 4GP, United Kingdom
Address
John Eccles HouseRobert Robinson Avenue,
Oxford Science Park, Oxford
OX4 4GP, United Kingdom