Hanford Site performance summary: EM funded programs
Author(s) -
C. Edwards
Publication year - 1995
Publication title -
osti oai (u.s. department of energy office of scientific and technical information)
Language(s) - English
Resource type - Reports
DOI - 10.2172/197797
Subject(s) - schedule , receipt , hanford site , work (physics) , procurement , fiscal year , operations management , engineering , business , waste management , finance , radioactive waste , accounting , management , economics , marketing , mechanical engineering
Hanford performance at fiscal year end reflects a three percent unfavorable schedule variance ($46.3 million*) which was an improvement over August 1995 ($46.3 million for September versus $65.9 million for August) and is below established reporting thresholds (greater than 3 percent). The majority of the behind schedule condition (53 percent) is attributed to EM-40 (Office of Environmental Restoration [ER]) and is a result of late receipt of funds, procurement delays, and US Army Corps of Engineers (USACE) work planned but not accomplished. Other primary contributors to the behind schedule condition are associated with tank farm upgrades, high-level waste disposal and work for others (support to the US Department of Energy-Headquarters [DOE-HQ]). The remaining behind schedule condition is distributed throughout the remaining Hanford programs and do not share common causes. A breakdown of individuals listed on page 8

The content you want is available to Zendy users.

Already have an account? Click here to sign in.
Having issues? You can contact us here
Accelerating Research

Address

John Eccles House
Robert Robinson Avenue,
Oxford Science Park, Oxford
OX4 4GP, United Kingdom