Development & Testing of Industrial Scale, Coal Fired Combustion System, Phase 3
Author(s) -
B. Zauderer
Publication year - 1998
Language(s) - English
Resource type - Reports
DOI - 10.2172/1976
Subject(s) - boiler (water heating) , combustor , nox , combustion , waste management , coal , environmental science , sorbent , engineering , chemistry , organic chemistry , adsorption
In the third quarter of calendar year 1997, 10 days of tests on the 20 MMBtu/hr combustor-boiler facility were performed. The total test days on the Philadelphia facility to the end of September 1997 was 93, of which 19 tests were implemented as part of another DOE project. This exceeds the planned 63 test days for this project. Key project objectives have been exceeded, including NO emissions as low as 0.07 lb/MMBtu and SO emissions as low as 0.2 x 2 lb/MMBtu. The tests in the present quarter focussed on further optimizing post-combustion sorbent injection for SO2 and NOx control processes. The results were in the same range as in previous tests. In addition, initial tests of Coal Techs post-combustion NOx control process were implemented on a 100 MW and a 37 MW utility boiler, and NOx reductions as high as 40% were measured in the latter boiler
Accelerating Research
Robert Robinson Avenue,
Oxford Science Park, Oxford
OX4 4GP, United Kingdom
Address
John Eccles HouseRobert Robinson Avenue,
Oxford Science Park, Oxford
OX4 4GP, United Kingdom