Building 9401-2 Plating Shop Surveillance and Maintenance Plan
Publication year - 1999
Publication title -
osti oai (u.s. department of energy office of scientific and technical information)
Language(s) - English
Resource type - Reports
DOI - 10.2172/14793
Subject(s) - plan (archaeology) , containment (computer programming) , plating (geology) , piping , engineering , waste management , business , operations management , computer science , environmental engineering , archaeology , geophysics , history , programming language , geology
This document provides a plan for implementing surveillance and maintenance (S and M) activities to ensure that Building 9401-2 Plating Shop is maintained in a cost effective and environmentally secure configuration until subsequent closure during the final disposition phase of decommissioning. U.S. Department of Energy (DOE) G430.1A-2, Surveillance and Maintenance During Facility Disposition (1997), was used as guidance in the development of this plan. The S and M Plan incorporates DOE O 430.1A, Life Cycle Asset Management (LCAM) (1998a) direction to provide for conducting surveillance and maintenance activities required to maintain the facility and remaining hazardous and radioactive materials, wastes, and contamination in a stable and known condition pending facility disposition. Recommendations in the S and M plan have been made that may not be requirement-based but would reduce the cost and frequency of surveillance and maintenance activities. During the course of S and M activities, the facility's condition may change so as to present an immediate or developing hazard or unsatisfactory condition. Corrective action should be coordinated with the appropriate support organizations using the requirements and guidance stated in procedure Y10-202, Rev. 1, Integrated Safety Management Program, (Lockheed Martin Energy Systems, Inc. (LMES), 1998a) implemented at the Oak Ridge Y-12 Plant and the methodology of the Nuclear Operations Conduct of Operations Manual (LMES, 1999) for the Depleted Uranium Operations (DUO) organization. The key S and M objectives applicable to the Plating Shop are to: Ensure adequate containment of remaining residual material in exhaust stacks and outside process piping, stored chemicals awaiting offsite shipment, and items located in the Radioactive Material Area (RMA); Provide access control into the facility and physical safety to S and M personnel; Maintain the facility in a manner that will protect the public, the environment, and the S and M personnel; Provide an S and M plan which identifies and complies with applicable environmental, safety, and health safeguards and security requirements; and Provide a cost effective S and M program for the plating shop, Building 9401-2
Accelerating Research
Robert Robinson Avenue,
Oxford Science Park, Oxford
OX4 4GP, United Kingdom
Address
John Eccles HouseRobert Robinson Avenue,
Oxford Science Park, Oxford
OX4 4GP, United Kingdom