SECOND GENERATION PFBC SYSTEMS R AND D - PHASE 2 AND 3
Author(s) -
A. Robertson
Publication year - 1999
Publication title -
osti oai (u.s. department of energy office of scientific and technical information)
Language(s) - English
Resource type - Reports
DOI - 10.2172/14003
Subject(s) - combustor , gas compressor , natural gas , phase (matter) , nuclear engineering , environmental science , engineering , waste management , combustion , mechanical engineering , chemistry , organic chemistry
When DOE funds were exhausted in March 1995, all Phase 2 activities were placed on hold. In February 1996 a detailed cost estimate was submitted to the DOE for completing the two remaining Phase 2 Multi Annular Swirl Burner (MASB) topping combustor test campaigns; in August 1996 release was received from FETC to proceed with the two campaigns to: (1) test the MASB at proposed demonstration plant full to minimum load operating conditions; (2) identify the lower oxygen limit of the MASB; (3) demonstrate natural gas to carbonizer fuel gas switching; and (4) demonstrate operation with ''low temperature'' compressor discharge air rather than high temperature ({approx}1600 F) vitiated air
Accelerating Research
Robert Robinson Avenue,
Oxford Science Park, Oxford
OX4 4GP, United Kingdom
Address
John Eccles HouseRobert Robinson Avenue,
Oxford Science Park, Oxford
OX4 4GP, United Kingdom