Safety analysis report for packaging upgrade plan
Author(s) -
D.L. Kelly
Publication year - 1998
Language(s) - English
Resource type - Reports
DOI - 10.2172/11278
Subject(s) - upgrade , plan (archaeology) , schedule , operations management , business , engineering management , engineering , operations research , computer science , operating system , geography , archaeology
This Safety Analysis Report for Packaging (SARP) Upgrade Plan reflects a revised SARP upgrade schedule based on the most current program needs. A Project Hanford Management Contract (PHMC) Performance Expectation exists to update, revise, and/or cancel seven onsite SARPS during FY 1999. It is the U.S. Department of Energy's desire that 100% of the SARPs (which existed at the beginning of the PHMC Contract) be upgraded, revised, and/or canceled by the end of the five year contract. This plan is a ''living'' document and is used as a management tool